Case Study
Transforming an Agricultural Warehouse into a State-of-the-Art Logistics Facility

Introduction
BSI Engineering partnered with a major agricultural products manufacturer to renovate an aging warehouse and transform it into a modern logistics hub. This $27 million project included comprehensive upgrades to utilities, administrative spaces, and logistics infrastructure to support the client’s just-in-time delivery requirements.
The result was a state-of-the-art facility that streamlined distribution operations, enhanced product handling efficiency, and provided the scalability needed to support the client’s expanding portfolio.
Discovery
The client sought a cost-effective solution to meet growing distribution needs. Challenges included:
- Upgrading a 70,000-square-foot warehouse and a 12,000-square-foot administrative building.
- Adding a tanker truck and rail loading/unloading structure.
- Meeting stringent safety and operational standards for hazardous chemical storage and handling.
Research
Extensive research was conducted to create a solution tailored to the client’s operational needs. BSI Engineering studied logistical flow patterns, hazardous material handling standards, and just-in-time delivery practices to inform the design. Benchmarking against industry standards, the team identified best practices for warehouse layouts, utility systems, and material handling infrastructure.
Utility assessments revealed the need for significant upgrades to HVAC, fire suppression, and electrical systems to support the expanded operations. Additionally, research into loading/unloading technologies ensured the new platforms would optimize turnaround times and reduce operational costs.
Planning
A comprehensive renovation plan was developed to meet the client’s goals:
- Facility Renovations: Upgraded the warehouse with hazardous process rooms, packaging lines, and a quality control lab.
- Utility Enhancements: Modernized HVAC, electrical, and water systems to support new operations.
- Logistics Infrastructure: Designed and built tanker truck and rail loading platforms for efficient distribution.


Delivery
Executing the project required meticulous coordination across multiple disciplines. BSI Engineering managed the procurement of critical components such as Siemens PLCs and SIS, High Temperature Custom Electric Heaters, and high-temperature valves. The facilities were equipped with advanced rotary traverse systems, gas analysis system, data acquisition system and high-temperature alloy designs to withstand the extreme conditions of combustor testing.
The construction process emphasized precision and quality control, with all systems rigorously tested before commissioning. Software programming for facility operation was integrated seamlessly, providing clients with a user-friendly interface for managing testing processes. The result was a pair of world-class test cells delivered on schedule and within budget.

Results
Results
The renovated facility delivered a 30% increase in distribution efficiency, significantly improving the client’s ability to meet just-in-time delivery demands. The addition of specialized logistical features reduced material handling times by 20%, while modernized utilities lowered operational costs by 15%.
The improved administrative spaces enhanced on-site management efficiency and employee satisfaction. This transformation positioned the client to scale operations and expand their market presence, showcasing the value of BSI Engineering’s comprehensive approach.

Faster distribution due to streamlined logistics processes.
Total project cost, delivered within budget.
Reduction in operating expenses from logistics consolidation.